Progress · Updated this month

Built in front of you.

Live percentage complete by trade, plus the latest site photos from the past 30 days.

Overall complete
57%
Handover
Q4 2026
Excavation & foundations100%
Substructure & basements100%
Superstructure72%
MEP installation38%
Façade & cladding22%
Interior finishing8%
Recent site photo, this month

Site photo — updated this month.

Get monthly progress updates

We'll email you new photos and milestone updates.